Transport of a Reactor for chemical plant in Tarragona|  April 2018

20180418_104436

Project description

Offloading, reception, transport and delivery of a reactor and spare parts for a chemical plant in Tarragona.

Commodity: One Reactor and spare parts for a chemical plant.
Weight Reactor: 112,000 Kg.

Execution time: from 14 March to 19 April 2018.

Work Scope:
Asta Logistik has rendered the offloading of the reactor and spares from a roro vessel in the port of Barcelona, transshipment from a roll-trailer to a low bed truck using two cranes working in tandem on the pier and special transport to a chemical plant in Tarragona.

Road and engineering studies were delivered to the different local and national administrations in charge for each section of the inland transport route.

Origin: Barcelona, Spain
Destination: Tarragona, Spain

Exceptional pieces:
One reactor: L 6.73 m x W 3.87 m x H 4.01 meters. Weight: 112,000 Kg.
One spare bolt: L 1.40 m x W 1.40 x H 1.15 meters. Weight: 2,800 Kg.
One spare gasket: L 3.00 m x W 3.00 x H 0.3 meters. Weight: 110 Kg.