First of a total of 6 or 7 shipments, for the transport until Mostaganem (Algeria) from the pipeline channeling and substations for a seawater desalination plant
Commodity: Pipeline channeling and substations for a seawater desalination plant in Mostaganem, Algeria.
Execution time of the project: de March 2010 a December 2010
First shipment: March 2010
Work scope: Ship's agency M/V. "HELGA" in Mostaganem, customs clearance, unloading and delivery on site of the water pipeline of 150 kilometers.
Coordination door to door of the containers from France and Spain until delivery in site in Mostaganem.
Origin: Antwerp, France and Spain
Destination: Mostaganem (Algetia)
Total weight and volume of the project: 40.000 Mtons and 80.000 cbm plus 600 containers
Weight and volume of the first shipment: 4.200 Mtons and 8.000 cbm
Exceptionals pieces:
Water piperlines from differents diameters (from 0,20 to 1,40 meters) and lengths (from 6 to 12 meters)