Since Bermeo, Castellón, Motril and Huelva until Arzew and Oran, port operations, loading of vessel, shipping and road transport of all components of a water desalination plant and machinery for the foundation of it.
Commodity: machinery to make the foundation of the plant, tanks, sand, filters, pipes and other components of the water desalination plant.
Execution time: one year, from November 2008 till December 2009
Work scope: ports operations, loading of vessels and shipping of a total of 12 shipments.
Origin: Bermeo, Castellón, Motril and Huelva (Spain)
Destination: Arzew and Oran (Algeria)
Weight and volume: 20.000 Tons and 80.000 cbm - total of 12 shipments
Exceptionals pieces: machinery of 84 Tons and
2 tanks of 32 m. long and 6 m. of diameter